Why 2nd Niger Bridge Is Delayed —FG

During the submission of his tenure report, the Minister of Power, Works and Housing Mr Babatunde Raji Fashola attributed the delay behind the slow pace of work on the N206billion 2nd Niger Bridge handled by Julius Berger Nigeria to water level.
He said the depth of water in the river was not what the contractor could contain, adding that the water level cannot be above 15 feet deep for them to work.

“During peak raining season it slows down their work because really you need divers to go under this is what it takes to build a bridge. So at the height of that raining season when there was flooding, work will slow down.”

They can work only about 15 meters depth of the River Niger Bridge, with the massive flooding that we have now it must be about 30 meters. So if you are doing 30 meters of water that is height of a 10 Storey building so they need to wait for it to come down.

According to him, “As the raining season ends you will see more activities there. Construction is not subject only to money, materials, and transportation it is also subject to weather.”

Total Views: 219 ,
0
0
READ ALSO  Protecting Concrete From Fire Damage Using Materials Recycled From Old Tyres

17 thoughts on “Why 2nd Niger Bridge Is Delayed —FG

  1. Pingback: engagement rings
  2. Pingback: 카지노사이트
  3. Pingback: movies
  4. Pingback: ignou report
  5. Pingback: satta king 2020
  6. Pingback: 카지노사이트
  7. Pingback: judi togel
  8. Pingback: Engineering
  9. Pingback: Study in Uganda
  10. Pingback: 메이저사이트

Leave a Reply

Your email address will not be published. Required fields are marked *