In October 2018, the Minister of Power, Works and Housing, Mr. Babatunde Fashola, had promised Nigerians that nationwide power supply will get better with an anticipated addition of 945 megawatts (MW) of electricity into the grid before the end of that year.
Fashola, had while speaking at a business breakfast meeting of the Nigeria-South Africa Chamber of Commerce in Lagos, had said then that additional power worth that volume would be generated to the national grid from the 450MW Azura Edo power plant; 215MW Kaduna power plant; 240MW Afam-V power plant and 40MW Kashimbilla hydro plant, by the end of 2018.
By his appraisal, the minister had explained that the power sector had recorded successful improvements in its generation, transmission and distribution sub-sectors, and added that these plants would take the generation capacity of the country to new heights.
But an analysis of operational data obtained from the office of the Vice President, Prof. Yemi Osinbajo, showed that power generation did not add that much as promised by the government by the end of December 2018, or even since the beginning of the year.
As a matter of fact, the data showed that while the average power generated and distributed to Nigerians in December 2018 was 4,093MW, the country in the first one month of 2019, had 3,952MW supplied to it, thus, representing a decline from the December 2018 level of generation by 141MW or 3.4 per cent.
Again, the data from the Advisory Power Team in Osinbajo’s office, indicated that out of the four power plants the government based its expectation of an extra 945MW electricity supply to the grid, only the 450MW-capacity Azura Edo power plant was on the grid while the other three were yet to come in.
By April 2018, Azura had however announced the completion of its plant, indicating that all of its three turbines with a collective output of 450MW were deployed in Nigeria’s national grid, to suggest that the government only had about 495MW of electricity to add from Kaduna, Afam and Kashimbila, but could not eventually.
How the Target Was Missed
Based on Fashola’s promise, and a review of subsequent developments at the three power plants that could have given the country additional 495MW since Azura was already producing energy ahead of the promise, we found that the government failed on this on account of sundry issues related to poor project management and financial commitments, as well as statutory parliamentary inquest.
For instance, during his visit to the 215MW Kaduna power plant, Fashola had said four out of the eight turbines installed at the site of the plant had been completed and ready to begin producing electricity to the national grid.
He said progress had been made at the plant since he last visited it about a year ago, noting that every megawatts of power that can be gotten from the plant would be added to the national grid.
“We have also tested four of the turbines, preparatory for commissioning, so there are essentially four turbines that are ready to go.
“So, every megawatt we can deliver from this project, considering that each of the turbines is 25 megawatts, is additional power.
“Clearly this will boost our incremental power objective and we are on our way. It will just take those man hours and those challenges to get to our destination,” the minister had explained.
But, the Project Manager at Rockson Engineering which was contracted to build the plant, Mr. Sunny Okwedi, explained that while four of the plants eight turbines had been completed and ready to be powered, they however would not be switched on until the Power Control Motor (PCM) was installed with the switch yard commissioned.